Town of Chapel Hill header
File #: [22-0752]    Version: 1 Name:
Type: Discussion Item Status: Filed
File created: 9/16/2022 In control: Town Council
On agenda: 10/12/2022 Final action: 10/12/2022
Title: Provide Guidance on Options for the Future of Franklin Street Downtown.
Attachments: 1. Draft Staff Presentation, 2. Survey Results, 3. Staff Presentation, 4. Emails from the Public
Related files: [21-0813], [22-0003], [22-0083]

title
Provide Guidance on Options for the Future of Franklin Street Downtown.
body

Staff:
Department:
Bergen Watterson, Transportation Planning Manager
Planning
Sarah Poulton, Senior Project Manager
Manager's Office

Overview: Franklin Street is Chapel Hill's "Main Street", serving as the primary commercial and social hub of the Town. The road is currently maintained by the North Carolina Department of Transportation (NCDOT) and W. Franklin St. recently became a two-lane road with bike lanes and parallel parking on both sides along some of the corridor. Town Council has expressed interest in transferring maintenance of Franklin Street from NCDOT which would allow the Town to consider additional bike, pedestrian, and commercial enhancements that are not currently allowed by NCDOT.

Staff created an informational presentation and survey, and conducted a FlashVote, to gather feedback from the public. The survey was open for two weeks and received 348 responses; FlashVote was open for 48 hours and got 362 responses.


Recommendation(s):
That the Council provide guidance on the options for Franklin Street Downtown. The final recommendation is dependent on what enhancements we would like to see on Franklin Street Downtown.

Decision Points:
* What additional bike, pedestrian and commercial-support enhancements does Council want to see Downtown?
* Should the Town request a transfer of maintenance of Franklin St. between Raleigh St. and Merritt Mill Rd. from NCDOT?

Key Issues:
* The cost to the Town for one-time upgrades needed at some point after taking over maintenance of approximately one mile of Franklin St. between Raleigh St. and Merritt Mill Rd. is estimated to be up to $2.7million, including major stormwater system replacements (see attached presentation for details).
o The annual cost of maintaining the road is estimated at approximately $190,000, which includes a new Stormwater employee dedicated to Franklin St.
* Town control of Franklin St. would allow m...