File #: [20-0190]    Version: 1 Name:
Type: Discussion Item Status: Filed
File created: 2/14/2020 In control: Town Council
On agenda: 3/4/2020 Final action: 3/4/2020
Title: Authorize the Town Manager to Finalize Arrangements for Construction of the Elliott Road Extension Project.

 

 

title

Authorize the Town Manager to Finalize Arrangements for Construction of the Elliott Road Extension Project.

body

 

Staff:

Department:

Lance Norris, Director

Public Works

Bergen Watterson, Transportation Planning Manager

Planning

 

Overview: On February 12, 2020 <https://chapelhill.legistar.com/LegislationDetail.aspx?ID=4327810&GUID=26AA1466-65BA-40FE-AD07-A9C9D8418960&Options=&Search=> staff provided an update on the Elliott Road Extension design and plans for construction. The roadway plans are nearly complete, and staff has negotiated a not-to-exceed cost for the road construction with BR Chapel Hill, LLC. Staff is seeking guidance on funding options for the increased cost.

 

Recommendation(s):

That the Council provide guidance on funding options and authorize the Town Manager to execute a reimbursement agreement with BR Chapel Hill, LLC to construct the road.

 

Key Issues:

                     The construction cost estimate is now higher than it was when Council authorized staff to proceed with construction in 2018.

                     The total cost to construct the road is estimated to be $7.1 million.

                     Construction is expected to begin in spring 2020.

 

Fiscal Impact/Resources: The original funding plan allocated $5 million to the Elliott Road Extension (Phase II). Due to a combination of project cost increases and project budget decreases that were discussed at the February 12, 2020 Council work session, there is a funding gap.

 

Where is this item in its process?

 

Attachments:

 

Resolution (to be distributed)

 

Reimbursement Resolution (to be distributed)

 

Staff Memorandum (to be distributed)

 

 

end

 

The Agenda will reflect the text below and/or the motion text will be used during the meeting.

 

presenter

PRESENTER: Bergen Watterson, Transportation Planning Manager

Lance Norris, Director of Public Works

 

RECOMMENDATION: That the Council provide guidance on funding options for Elliott Road Extension and authorize the Town Manager to execute a reimbursement agreement with BR Chapel Hill, LLC to construct the road.