Title: Discuss Options for the Fordham Boulevard Sidepath Project.
Attachments: 1. Staff Memorandum, 2. Draft Staff Presentation, 3. Noise Monitoring Memorandum, 4. Sidepath Construction Clearing Limits, 5. October 2019 StealthStat Data, 6. Proposed Landscape Plans, 7. Transportation and Connectivity Advisory Board Recommendation, 8. Staff Presentation, 9. Council Questions with Staff Response, 10. Emails from the Public

 

 

title
Discuss Options for the Fordham Boulevard Sidepath Project.

body

 

Staff:

Department:

Judy Johnson, Interim Director

Planning

Bergen Watterson, Transportation Planning Manager

 

Bill Webster, Planning and Development Manager

Parks and Recreation

 

Overview: The purpose of this item is to present information on design options for a pedestrian and bicycle facility along Fordham Boulevard from Cleland Drive to Willow Drive.

 

Recommendation(s):

That the Council review options for the Fordham Boulevard Sidepath project.

 

Key Issues:

                     Residents of the Little Ridgefield neighborhood (adjacent to the proposed sidepath) have expressed concerns about safety, noise, and loss of vegetative buffer along Fordham Blvd.

                     The residents proposed a ‘shared street <https://nacto.org/publication/urban-street-design-guide/streets/residential-shared-street/>’ concept from Ridgefield Road to Willow Drive, which would route bicycles and pedestrians onto neighborhood streets where they would share low-speed, low-volume roads with vehicles.

                     A design consultant developed three alternate designs for the segment between Ridgefield Road and Willow Drive:

o                     A sidepath running along Fordham Boulevard as originally proposed

o                     A shared street along Hickory Drive

o                     A shared street along Hickory Drive with a sidewalk on one side

                     Staff and the consultant have prepared materials to address the noise and vegetative buffer concerns raised by residents.

o                     Noise analysis and memorandum

o                     Illustrated clearing limits for sidepath construction

o                     Proposed landscape plans, including cross-section diagrams

                     Staff will return on March 4, 2020 to ask for Council to approve a design alternative for the project.

 

Fiscal Impact/Resources: The project has an approved budget of $1,058,000, which includes $846,400 in federal funds (80%) and a local match of $211,600 (20%) from the 2015 Transportation Bond.

 

Where is this item in its process?

 

Attachments:

 

Staff Memorandum

 

Draft Staff Presentation

 

Noise Monitoring Memorandum

 

Sidepath Construction Clearing Limits

 

October 2019 StealthStat Data

 

Proposed Landscape Plans

 

Transportation and Connectivity Advisory Board Recommendation

 

end

 

The Agenda will reflect the text below and/or the motion text will be used during the meeting.

presenter

PRESENTER: Bergen Watterson, Transportation Planning Manager

 

RECOMMENDATION: That the Council review options for the Fordham Boulevard Sidepath project.