Legislation Details

File #: [26-0309]    Version: 1 Name:
Type: Consent Status: Agenda Ready
File created: 9/8/2026 In control: Town Council
On agenda: 9/23/2026 Final action:
Title: Approve a Construction Contract to Remediate the Dam at 1714 Legion Road
Attachments: 1. Construction Contract to Remediate the Dam Resolution, 2. Budget Ordinance - Stormwater Fund, 3. Project Ordinance - 2024 Affordable Housing Bonds Fund, 4. RESOLUTION_AMERICAN_LEGION_PROPERTY_2016-12-05 (1), 5. A RESOLUTION APPROVING THE RECOMMENDATIONS OF THE LEGION PROPERTY COMMITTEE AND AUTHORIZING THE TOWN MANAGER TO PROCEED WITH NEXT STEPS (2022-12-07R-11) (3) (1), 6. Legion Pond - Chapel Hill - Report Final 5-10-23, 7. Tetra Tech - Legion Property Pond Memo
Related files: [20-0110], [22-0486], [22-0915], [23-0432], [23-0451], [24-0327]
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
AGENDA ITEM EXECUTIVE SUMMARY
ITEM TITLE
title
Approve a Construction Contract to Remediate the Dam at 1714 Legion Road
presenter
RESPONSIBLE STAFF, TITLE, DEPARTMENT
Lance Norris, Director, Public Works
Chad Brown, Capital Projects Manager, Engineering
STAFF RECOMMENDATION*
Adopt the attached resolution awarding a bid to Morgan Corp. and authorizing the Town Manager to execute a contract with this lowest responsive, responsible bidder.
body
ACTION/DECISION POINTS*
Council must authorize or deny the Town Manager's approval of change orders as necessary, provided the contract cost remains within the budgeted amount.
LEGISLATIVE CONTEXT*
N.C. General State Statue 143-129 https://www.ncleg.net/EnactedLegislation/Statutes/HTML/BySection/Chapter_143/GS_143- sets the procedure for letting public contracts.
BACKGROUND AND CONTEXT*
On December 5, 2016, a resolution (2016-12-05/R-8) was passed authorizing the Town Manager to execute an offer to purchase and contract and lease for the American Legion Property. The resolution stated that the acquisition of the Legion property allows the Town the opportunity to move forward with uses that benefit community.
On December 7, 2022, a resolution (2022-12-07/R-11) was passed approving the recommendations of the Legion Property Committee and authorizing the Town Manager to proceed with next steps including:
Retaining ownership of the entire property,
Combining approximately 27 acres of the property with Ephesus Park for a Town park,
Using 8-9 acres along Legion Road for affordable housing,
Preserving existing natural areas, and
Determining the best placement of stormwater feature(s) on the site which might include a reduced pond.
A May 2023 Preliminary Engineering Report prepared by Garrett & Moore Engineering confirmed that the existing pond dam was classified as Class C, or High Hazard Dam, in which a dam failure could become possible to the detriment of downstream properties and recommended the Town proceed with the work...

Click here for full text