File #: [19-0376]    Version: 1 Name:
Type: Discussion Item Status: Passed
File created: 3/26/2019 In control: Town Council
On agenda: 4/24/2019 Final action: 4/24/2019
Title: Consider a Memorandum of Understanding and Agreement for Sharing Costs for Improvements to High School Road in Conjunction with the Chapel Hill-Carrboro City Schools Chapel Hill High School Redevelopment and Maintenance Building Projects.
Attachments: 1. Draft Staff Presentation, 2. Technical Report, 3. High School Road MOU 320 draft, 4. Staff Presentation, 5. Council Questions with Staff Response, 6. A RESOLUTION APPROVING A MEMORANDUM OF UNDERSTANDING AND AGREEMENT FOR SHARING COSTS FOR IMPROVEMENTS TO HIGH SCHOOL ROAD IN CONJUNCTION WITH CHAPEL HILL-CARRBORO CITY SCHOOLS CHAPEL HILL HIGH SCHOOL REDEVELOPMENT AND MAINTENANCE BUILDING PROJECTS (2019-0, 7. AN ORDINANCE TO AMEND “THE ORDINANCE CONCERNING APPROPRIATIONS AND THE RAISING OF REVENUE FOR THE FISCAL YEAR BEGINNING JULY 1, 2018” (2019-04-24/O-3)


title
Consider a Memorandum of Understanding and Agreement for Sharing Costs for Improvements to High School Road in Conjunction with the Chapel Hill-Carrboro City Schools Chapel Hill High School Redevelopment and Maintenance Building Projects.
body

Staff:
Department:
Maurice Jones, Town Manager
Manager's Office
Ralph Karpinos, Town Attorney
Town Attorney's Office
Kumar Neppalli, Traffic Engineer
Public Works
Judy Johnson, Planning Operations Manager
Planning

Overview: The attached Memorandum of Understanding and Agreement proposes adjustments to the planned road improvements along High School Road associated with the approved special use permit modifications for the Chapel Hill High School (under construction) and the Schools' Maintenance Building (not yet under construction).

Under the proposed Cost-Share Agreement, the approved bike lanes on both sides of High School Road would be eliminated. Instead, the Schools would construct an off-road combined bicycle-pedestrian pathway allowing the Schools substantial cost savings for the High School project underway and avoiding future expenses associated with the Maintenance Building project.

Based on changes to State Law enacted while the High School Special Use Permit Modification application was pending, the Agreement proposes that the costs of the revised improvements be shared by the Schools and the Town, as explained in more detail in the attached Technical Report.


Recommendations:
That the Council approve the Memorandum of Understanding and Agreement to adjust the High School Road improvement plans and to share the costs of the road improvements; and,
That the Council enact the attached budget ordinance amendment to allocate funding up to $200,000 as the Town's share of the bicycle/pedestrian improvements. The Town would also cover expenses associated with the SUP-stipulated bus shelter within this monetary limit.

Decision Points:
* Does the Council approve of the change from an on-road bike lan...

Click here for full text