File #: [24-0274]    Version: 1 Name:
Type: Consent Status: Passed
File created: 5/3/2024 In control: Town Council
On agenda: 5/15/2024 Final action: 5/15/2024
Title: Approve a Contract to Perform Maintenance of Town-Owned Stormwater Control Measures (SCMs).
Attachments: 1. ToCH Facilities with SCMs for Inspections Contract 2024-03-01, 2. A RESOLUTION to AWARDING A CONTRACT FOR MAINTENANCE OF TOWN-OWNED STORMWATER CONTROL MEASURES TO TRIANGLE POND MANAGEMENT IN THE AMOUNT OF $690,775. (2024-05-15/R-5)
title
Approve a Contract to Perform Maintenance of Town-Owned Stormwater Control Measures (SCMs).

body

Staff:
Department:
Lance Norris, Director
Public Works
Chris Roberts, Manager of Engineering

Rob Gehris, Engineer III


Overview: The purpose of this item is to recommend that the Council award a bid to Triangle Pond Management, of Raleigh, NC, for rehabilitation of select Town-owned stormwater control measure (SCM) facilities.


Recommendation(s):
That the Council:
* adopt the attached resolution awarding a bid and authorizing the Town Manager to execute a contract with the lowest responsive, responsible bidder, TRIANGLE POND MANAGEMENT, in an amount of $690,775.

Key Issues:
* The Town contracted an engineering firm (AECOM) to inspect Town-owned stormwater control measures (SCM). The resulting report identified 31 Town-owned SCMs in need of rehabilitation.

* Town has an obligation as a municipal separate storm sewer system (MS4) operator to maintain the Town-owned SCMs. This SCM maintenance contract is needed to comply with the State's National Pollutant Discharge Elimination System (NPDES) permitting requirements.

* The Town solicited formal bids for SCM rehabilitation and received one responsive bid. The town re-bid the project to a wider variety of contractors, and still received one responsive bid to the re-issued request for bid. A total of ten contractors were in attendance at a required pre-bid meeting.

* Triangle Pond Management was determined to be the lowest responsive, responsible bidder.

Fiscal Impact/Resources: The project budget comes from the Stormwater Enterprise Fund in the amount of $690,775.


Attachments:

Resolution

List of Town-owned SCM facilities to be rehabilitated







A RESOLUTION to AWARDING A CONTRACT FOR MAINTENANCE OF TOWN-OWNED STORMWATER CONTROL MEASURES TO TRIANGLE POND MANAGEMENT IN THE AMOUNT OF $690,775. (2024-05-15/R-5)

WHEREAS, thirty-one Town-owned stormwater control measures (SCMs) were identifie...