Legislation Details

File #: [23-0763]    Version: 1 Name:
Type: Consent Status: Passed
File created: 9/30/2023 In control: Town Council
On agenda: 10/25/2023 Final action: 10/25/2023
Title: Award a Bid and Authorize the Town Manager to Execute a Contract for the Construction of Intersection Improvements at North St. / Martin Luther King Jr. Blvd./ North Columbia St.
Attachments: 1. A RESOLUTION AUTHORIZING THE TOWN MANAGER TO EXECUTE A CONTRACT WITH CINDERELLA PARTNERS, INC., IN AN AMOUNT OF $874,133.43 FOR INTERSECTION IMPROVEMENTS AT NORTH ST. / MARTIN LUTHER KING JR. BLVD./ NORTH COLUMBIA ST. PROJECT (2023-10-25/R-4)

title

Award a Bid and Authorize the Town Manager to Execute a Contract for the Construction of Intersection Improvements at North St. / Martin Luther King Jr. Blvd./ North Columbia St.

body

 

Staff:

Department:

Lance Norris, Director

Public Works

Roger Henderson, Transportation Engineering Manager

 

 

Overview: We recommend that the Council award a bid to Cinderella Partners, Inc. to construct intersection improvements at North St. /Martin Luther King Jr. Blvd/North Columbia St. The project will reconfigure the intersection to better align North St. with North Columbia St. This project will also include a new traffic signal and pedestrian crosswalks at the intersection.

 

Recommendations:

That the Council:

•                     Adopt the attached resolution awarding a bid and authorizing the Town Manager to execute a contract with the lowest responsive, responsible bidder, Cinderella Partners, Inc., in an amount of the submitted bid of $874,133.43.

•                     Authorize the Town Manager to approve change orders as necessary provided that the contract cost remains within the budgeted amount.

 

Key Issues

•                     Intersection improvements at North St./ Martin Luther King Jr. Blvd./ North Columbia St. will support the smooth operation of the new Rosemary Parking Deck and make access to North Columbia St. easier as they exit the deck.

•                     These improvements were anticipated in the design of the Rosemary Parking Deck.

•                     The Town advertised the project for bid on August 7, 2023, and held a non-mandatory pre-bid conference on August 14, 2023. The Town received no bids on August 28, 2023. 

•                     The Town re-advertised the project for bid on September 25, 2023, and held a non-mandatory pre-bid conference on September 28, 2023. The Town received one bid on October 16, 2023. 

•                     Staff qualified Cinderella Partners, Inc., as the lowest responsive, responsible bidder.

•                     Staff anticipates that the contractor will begin the project in Fall 2023 with completion in mid to late Spring 2024.

 

Fiscal Impact/Resources: The project budget comes from the 2015 Streets and Sidewalk Bond funds in the amount of $874,133.43 for a total budget of $1.1 million including contingency.

 

 

 

Attachments:

 

• Resolution

 

 

 

 

 

 

 

 

 

 

 

 

 

A RESOLUTION AUTHORIZING THE TOWN MANAGER TO EXECUTE A CONTRACT WITH CINDERELLA PARTNERS, INC., IN AN AMOUNT OF $874,133.43 FOR INTERSECTION IMPROVEMENTS AT NORTH ST. / MARTIN LUTHER KING JR. BLVD./ NORTH COLUMBIA ST. PROJECT (2023-10-25/R-4)

 

WHEREAS, the Town of Chapel Hill solicited formal bids for construction of intersection improvements at North St./ Martin Luther King Jr. Blvd./ North Columbia St. on the Town website on August 7, 2023 and in accordance with N.C. General Statute Sec. 143-129; and

 

WHEREAS, the Town of Chapel Hill held a non-mandatory pre-bid conference on August 14, 2023 and September 28, 2023; and

 

WHEREAS, one responsive bid was received and opened on October 16, 2023; and

 

WHEREAS, the responsive bid was evaluated and Cinderella Partners, Inc. was determined to be the lowest responsive, responsible bidder; and

 

WHEREAS, the Cinderella Partners, Inc., bid amount is $874,133.43; and

 

WHEREAS, the current budget for this project is $1.1 million; and

 

NOW, THEREFORE, BE IT RESOLVED by the Council of the Town of Chapel Hill that the Council authorizes the Town Manager to execute a contract with the lowest responsive, responsible bidder, Cinderella Partners, Inc. in an amount of $874,133.43.

 

BE IT FURTHER RESOLVED that the Town Manager is authorized to approve change orders as necessary provided that the contract cost remains within the amount budgeted of $1.1 million.

 

This the 25th day of October, 2023.end

end

 

 

 

 

The Agenda will reflect the text below and/or the motion text will be used during the meeting.

 

presenter

By adopting the resolution, the Council awards a bid in an amount of $874,133.43 to Cinderella Partners, Inc., for the construction of intersection improvements at North St. / Martin Luther King Jr. Blvd. / North Columbia St.